Sunday, November 28, 2010

Finally...a little color!

The siding is underway...




Drywall in the great room done:


Porter's bath tub is in:

Sunday, November 21, 2010

Drywall!

The drywall in the first & second floors was hung this past week....exciting! It's starting to look like a real house now!





Sunday, November 14, 2010

Cement poured.

They poured the cement in the basement & garage this past week...





All inspections were signed off on as well, so this next week will bring the start of: elevator installation, insulation, drywall, stone work, & siding, which has already started!

It's starting to feel real now.

Monday, November 8, 2010

In Between.

This has been an "in between" week for the house progress...Right now, we're in between the electrical inspection, the heating inspection, the framing inspection...yawn...boring!...but all necessary. That should all be done by Wednesday, so they can then start on the insulation, siding, stone, basement framing...stuff that's fun to watch! Until then...

There is still progress being made. They have installed the heating pipes for the garage & basement floors:




The outside recessed lights are in: