Saturday, December 25, 2010

Hardwood floors...oh my!

Due to the chaos that is our life, we haven't made it up to the house in over two weeks (gasp!), but our builder sent us a few pictures he snapped last week.

The hardwood floors on the main level should be fully installed by now:


The basement is now fully framed with the drywall ready & waiting as soon as the framing inspection clears:


Up next: cabinets! Woot!

Thursday, December 9, 2010

Little by little.

Things are slowly taking shape inside...the moulding on the first & second floors is almost done.


The interior doors on both these floors are also done, but THEY ARE THE WRONG DOORS, so I didn't take any pictures of them. *Sigh*
Ah well....rewind & start again!

The stairway is well on its way:


It's kind of hard to see, but the shakes are now on the dormers, although they still need to be painted, so they are not final yet:

Sunday, November 28, 2010

Finally...a little color!

The siding is underway...




Drywall in the great room done:


Porter's bath tub is in:

Sunday, November 21, 2010

Drywall!

The drywall in the first & second floors was hung this past week....exciting! It's starting to look like a real house now!





Sunday, November 14, 2010

Cement poured.

They poured the cement in the basement & garage this past week...





All inspections were signed off on as well, so this next week will bring the start of: elevator installation, insulation, drywall, stone work, & siding, which has already started!

It's starting to feel real now.

Monday, November 8, 2010

In Between.

This has been an "in between" week for the house progress...Right now, we're in between the electrical inspection, the heating inspection, the framing inspection...yawn...boring!...but all necessary. That should all be done by Wednesday, so they can then start on the insulation, siding, stone, basement framing...stuff that's fun to watch! Until then...

There is still progress being made. They have installed the heating pipes for the garage & basement floors:




The outside recessed lights are in:

Sunday, October 31, 2010

Basement

The basement steps are in now, so I was able to go down & check it out. They've been busy working on heating & electrical this past week...They plan to wire for the elevator on Monday & pour cement on Wednesday. Movin' right along!

A few shots from the basement:









Try to contain your excitement.

Sunday, October 24, 2010

Windows in!

The windows are all in...Just in time for the deep freeze that we know is looming.





Windows on sides of front door now in place:


Porter got to see his new room today!

Saturday, October 16, 2010

The roof...the roof...the roof is...ON!!!

They shingled the roof this week!


Also started on the windows:


Fireplace is in:


Oh...and in case you're interested...they took away Porter's 'usual' bathroom stop, so today we had to find another one. Good thing there is a lot of construction going on in our neighborhood! We are now using Jimmy's Johnnys. Has a nice ring to it, don't you think?

Tuesday, October 12, 2010

A glimpse inside...

We got to go "inside" our new home today to discuss some framing options with our builder. It was so cool to actually start to visualize the layout. To quote Blair: "Okay, now even I'm excited!"

Bonus room:


Sunroom:


Corner of kitchen with window looking out the back:


Great room:


And this I just had to take a picture of. In order to get Blair into the house, they had to lift him on this big "thing" they move roof plywood with. There are probably 112 good jokes I could insert here, but I'll refrain...

Saturday, October 9, 2010

All covered up.

All the plywood has been added to the roof & it's ready for shingles.





Front door:

...although there should be double-hung windows on each side, so......yeah. We're looking into it. Stay tuned.

Sunday, October 3, 2010

Dry Weather = Progress!

We lucked out with good, dry weather this week, so the framers got a lot more done. Check it out:


The roof trusses are almost done & our builder says they hope to start the roof this next week!




The pond in the middle of our new neighborhood:


Our future new street:

Sunday, September 26, 2010

Movin' On Up!

They started framing the second level this week...Awesome!

View from the back...You can now see the start of Porter's room in the back corner upstairs.


Bonus room above the garage is started...


Kind of hard to see, but we now have stairs too!

Saturday, September 18, 2010

Frame it up.

The framing on the main level is near completion! Or at least it looks that way to us...We really have no idea.

There is a pile of wood in the way, but behind that is where the front door will be!


Side view of the garage...


Sunroom off the back...



Oh, this? What's this, you ask? Well, every single time we drive out to look at the house, we get there & Porter has to go to the bathroom. Every. Single. Time. And yes, every single time we have to use this port-a-potty. Every. Single. Time. I mean, I know we are very lucky it is there because who knows what Plan B would be, but...seriously?

Sunday, September 12, 2010

Second verse, same as the first.

Some more framing pictures--but it's cool to start to see where walls & windows will be!

Our future view through the great room windows...


Master bedroom wall/windows...